Over the past week, we've had two design meetings with Peter and Henry to finalize the floor and bathroom plans and then window schedule. We've got the floor plans more or less nailed out at this point, with a few final changes being made in the master suite. Stay tuned for more details on the new layout. Meanwhile, Henry is getting started with framing the interior walls for the downstairs rooms. Next week, we'll have another design meeting for the kitchen.
We're also preparing for the hurricane...putting plywood over one of the windows that got broken during deconstruction, and Billy, our mason, is at the house today securing the foundation. He is finishing the brick work and replacing several of the basement windows.
We hope everyone is well-prepared for the storm! And thanks to whichever neighbor pulled up the silt sock that we placed around the drain.